LAWRENCE, Kan.  - Aquatherm Pipe has published a case study on a project at Berry Global, which was completed by ×îÐÂÂ鶹ԭ´´ Group.

Berry’s Lawrence plant produces food-grade plastic cups and containers, operating 24/7 all year long. The plant uses an injection molding system and the steel piping that circulated cooling water was corroding, slowing the process down.

blog 3

Since about 300 feet of piping needed to be replaced, Berry was facing significant and very expensive downtime. Jacob Francis, Berry’s facility maintenance supervisor, worked with Todd Mihalchik, ×îÐÂÂ鶹ԭ´´ Group project manager, on alternative solutions. They chose to replace the old steel piping with Aquatherm Blue Pipe.

It took ×îÐÂÂ鶹ԭ´´ about 24 hours to install the Aquatherm. It is much lighter, will not corrode and it needs no insulation in most interior spaces. In addition to the piping install, ×îÐÂÂ鶹ԭ´´ Group built and installed a 12,500 gallon cooling tank for the system.