Southern Hills Hospital
The initial project scope for ×îÐÂÂ鶹Դ´ was to add one patient floor to the hospital, with upgrades to the powerhouse chiller and boilers. But multiple large change orders added significantly to the project, adding another floor as shell space along with booster pump change (original to the hospital) and new medical air and vacuum equipment.
The new medical air/ vacuum change was done live with no interruption to the hospital.
The original phasing was shown to be done in 15 phases over 24+ weeks. Working with JE Dunn, ×îÐÂÂ鶹Դ´ helped get the work done in only four phases and in 12 weeks. The work was completed exactly on schedule with no unplanned impacts to patients, no safety issues, and no quality concerns.
Watch the progress below:
Services Provided
-
HVAC construction
-
Plumbing construction
-
Sheet metal construction
Project Details
Las Vegas, NV
April, 2024
JE Dunn
Need a team of professional specialty contractors to help with your next construction project? Get started by finding a ×îÐÂÂ鶹Դ´ Construction location near you.
Still not sure if ×îÐÂÂ鶹Դ´ Construction, LLC is the right fit? Feel free to check out more examples of our past work and hear from our statisfied customers.